Well, all the trash is now removed. I hauled off 4,420 lbs of trash to be exact. Replacing all the electric in the kitchen has now began. Plenty of power will be laid out for xenon under cabinet lighting, small appliances, & power in the island also there will be cable tv and power in the cabinet above the microwave for a large flat screen tv. Its taking a little longer than expected because the existing wiring was in very bad shape. After all that is finished I will insulate and then up with the new drywall. The Solid maple 3/4 inch hard wood floor has arrived and waiting for installation. Thursday we took all the final measurements for the cabinets. They will be going into production sometime this week. They are also solid soft maple.